Madras High Court

Chennai HC: Arbitration Extension Granted Amid Witness Examination

Updated
Mar 7, 2026 11:11 AM
chennai-hc-arbitration-extension-granted-amid-witness-examination

Summary: The High Court in Chennai has given an extra six months for the arbitration between Dr. M. Subramanian and M/s. Hire and Build Technology Services Pvt. Ltd. This decision was made on February 23, 2026, by Judge N. Anand Venkatesh.

Case Background

Dr. M. Subramanian, along with Dr. S. Meenakshi and Dr. S. Meyyappan, filed a request against M/s. Hire and Build Technology Services Pvt. Ltd., located in Chennai. The case involves arbitration that needed more time to finish.

The Need for Extension

The arbitration was at the stage where witnesses from M/s. Hire and Build Technology Services Pvt. Ltd. were being questioned. Dr. M. Subramanian, speaking for himself, asked for more time. He pointed out a Joint Memo from August 9, 2025, where M/s. Hire and Build Technology Services Pvt. Ltd. had agreed to the extra time.

"The first applicant appeared in person and submitted that arbitration proceedings is now at the stage of examination of witness on the side of respondent."

Decision by the Court

Judge N. Anand Venkatesh agreed to give six more months for the arbitration to finish. This extra time starts from the day they get the order.

"In view of the above, time is extended for completion of arbitration proceedings by six (6) months from the date of receipt of a copy of this order."

What's Next?

The order was issued on February 23, 2026, and Dr. M. Subramanian and M/s. Hire and Build Technology Services Pvt. Ltd. now have more time to wrap up the arbitration process. This decision is to make sure all steps are properly completed.

Tags:
Arbitration
Civil Procedure
Commercial Disputes