Bombay High Court

Bombay High Court: Contractual Errors in Central Railway vs. A-1 Laundry Case

Updated
Dec 6, 2025 10:51 PM
bombay-high-court-contractual-errors-in-central-railway-vs-a-1-laundry-case

Quick Summary: Central Railway and A-1 Laundry Services got into a legal fight over a contract disagreement. The court made decisions on several issues, with both sides having some wins and losses.

The Contract and Dispute

Central Railway hired A-1 Laundry Services to manage a laundry facility in Mumbai. The deal, worth over 79 crores, was supposed to last 15 years. However, problems arose over missing laundry and fines. The case went to an Arbitration Panel, which decided A-1 Laundry should get nearly 4.9 crores. Central Railway disagreed and took it to court.

The Judges and the Decision

Judge Sandeep V. Marne made the final decision. The court was asked to see if the panel's decision was fair and if it followed the contract rules. It turned out, the panel had made some mistakes, using railway guidelines instead of following the contract.

Claim 1: Lost Linen Costs

A-1 Laundry was supposed to pay for missing laundry at the price of new items. But the panel reduced this to 75% based on railway guidelines. The court said this was wrong and canceled this part of the decision.

Claim 2: Delay Penalties

The panel found that fines for delays were wrongly calculated by Central Railway. The court agreed with this, stopping more fines from being added.

Claim 3: Penalty Cap

The contract limited fines to 10% of the bill. The panel followed this limit, and the court agreed, keeping this part of the decision unchanged.

Claim 5: COVID-19 Compensation

A-1 Laundry wanted money for the time lost during COVID-19. The panel awarded them over 2.6 crores based on a railway guideline. But the court said no, since the contract didn't allow for this kind of payment.

Electricity Charges and Other Claims

The panel awarded A-1 Laundry for electricity costs, and the court agreed with this. Other requests like water charges and labor costs were denied.

Final Outcome

The court changed the amount A-1 Laundry would receive to about 1.73 crores with interest. Both sides had some wins and losses in this case.

Tags:
Contract Law
Arbitration
Commercial Dispute