
Here's a breakdown of a recent court case involving construction delays and arbitration in Aurangabad.
The case was between the Command Area Development Authority in Aurangabad and Hule Constructions Private Limited, led by Vishwanath Dagdoba Hule. The case also involved the State of Maharashtra's Water Resources Department.
The disagreement started when the Command Area Development Authority hired Hule Constructions to fix and upgrade 19 irrigation tanks in Beed, Maharashtra. The project was supposed to be finished by November 16, 2007, but was delayed by three years.
Hule Constructions said the delays happened because the Authority didn't finish necessary surveys on time. They asked for a formal process to get compensation for these delays. This process started after several appeals and a special civil case filed in 2012.
Hule Constructions made several claims, including:
The sole person deciding the case partly agreed with some claims, awarding Hule Constructions a total of Rs. 10,54,54,600. The Command Area Development Authority challenged this decision, saying that the process went beyond its limits and broke contract terms.
The Authority's main points were:
Judges Vaishali Patil-Jadhav and Arun R. Pedneker dismissed the appeal on January 29, 2026. They found no mistake in the arbitration process and noted that the Authority was responsible for the initial delays. The court upheld the decision to award compensation to Hule Constructions.
The Authority asked to pause the judgment, but it was denied. The court decided no further pause was needed since the appeal was dismissed.
In summary, the court ruled in favor of Hule Constructions, confirming that they deserved compensation due to the delays caused by the Authority.