Summary: On January 22, 2026, the Madras High Court told the Tahsildhar of Chinna Salem Taluk to measure and mark Sengottaiyan's property within 12 weeks. This decision was made after a delay in addressing Sengottaiyan's request from December 2025.
Sengottaiyan went to the court because his request for a land survey was ignored. On December 17, 2025, he asked the Tahsildhar of Chinna Salem Taluk, Kallakurichi District, to measure and mark the boundaries of his property. Since nothing happened, he filed a formal request for help.
Justice Abdul Quddhose heard the case and decided on January 22, 2026. The court told the Tahsildhar to carry out the survey and marking within 12 weeks from receiving the court's order. The court pointed out that there would be no harm to the Tahsildhar by considering Sengottaiyan's request.
"No harm will be caused to the respondent, if the aforementioned request of the petitioner is considered." - Justice Abdul Quddhose
The court outlined clear steps for the Tahsildhar:
Notify Neighbors: Before starting the survey, the Tahsildhar must inform neighboring landowners and any other relevant parties.
Consider Objections: If there are objections, they must be looked into before proceeding.
Police Assistance: If needed, the Tahsildhar can ask for police help to ensure the survey is conducted smoothly.
The court's decision ensures that Sengottaiyan's request is finally addressed, with specific instructions to prevent further delays.