Bombay High Court

District Court, Pune: Rajasthan Federation Must Pay for Construction Dispute

Updated
Nov 4, 2025 10:40 AM
News Image

Here's the scoop on the recent court decision involving the Rajasthan State Co-op Oil Seed Growers Federation Ltd. and B.G. Shirke Construction Technology Pvt. Ltd. This case revolves around a disagreement over payment for construction projects in Rajasthan.

The Dispute: Silos and Payments

Back in the late '80s, the Rajasthan Federation wanted to set up mustard seed storage units in three locations. They hired NHEC as the project manager, who then hired Shirke to do the actual construction work. The work was completed, but when Shirke asked for payment, things got complicated.

"On April 4, 1994, Shirke made a claim for a sum of Rs. ~4.83 lakh."

The Arbitration Twist

NHEC suggested that the disagreement should go to arbitration, and the court agreed. A group of arbitrators was set up, and in 2003, they decided that both the Rajasthan Federation and NHEC owed Shirke the money.

"On June 2, 2003, an arbitral award was passed awarding Rs. ~4.83 lakh coupled with interest."

Contesting the Award

The Federation wasn't happy. They argued that they had no direct contract with Shirke and shouldn't have to pay. They took the matter to the District Court, which supported the arbitrators' decision but ruled that NHEC was just a middleman and not responsible for paying.

"On July 18, 2013, the District Court, Pune upheld the Arbitral Award but also ruled that NHEC was merely an agent."

Court's Final Say

Judge Somasekhar Sundaresan reviewed the case. He concluded that the Federation was indeed part of the contract, even if they didn’t sign it directly. The court found that the Federation had been involved in the project and arbitration process, making them responsible for the payment.

"Tilam Sangh is a veritable party to the Agreement. Therefore, the Arbitral Award is not without jurisdiction over Tilam Sangh."

Key Takeaways

  • Federation's Responsibility: The court ruled that the Federation had to pay Shirke.
  • NHEC's Role: NHEC was considered a middleman and not responsible for the payment.
  • Authority: The court found that the arbitration group had the right to make the decision against the Federation.

This case highlights the complexities of contract law and arbitration, especially when multiple parties and agreements are involved. It's a reminder of the importance of understanding contractual obligations and the potential implications of arbitration clauses.